Prime Dome Construction

From ToorCamp Wiki
Revision as of 07:36, 22 June 2024 by Sasquatch (talk | contribs) (tools needed for building)
Jump to navigation Jump to search


Length Table

A	Yellow	3.958	47.496
B	Blue	4.638	55.656
C	Red	4.429	53.148
D	Black	4.938	59.256
E	Green	4.562	54.744
F	Orange	4.821	57.852
G	Silver	5.013	60.156
H	Pink	5.243	62.916
I	Brown	5.274	63.288

Side 26.916 29.916 Height 23.30993977 26.30993977


Tools

2 impact drivers, 4 chargers, 6 batteries(previously 2ah but bigger are mote available now) a ratchet, 3 correct size sockets with impact . 2 channel lock style pliers big enough to grab wing nuts.

member construction

Drill bit drill cuttoff wheel, measuring tape, press to squish the member ends flat, flap disk or grinder to deburr.

bolt specifications head size uses x socket

Tarp notes

Labor

A small crew is normally dedicated to this task. It normally takes about 2 days.

Safety

This may not be a complete list. 
  • Ask questions, see something say something.
  • We have deburred conduit, but there may still be sharp things.
  • Team lift, communication and coordination of the team is important.
  • Closed toe shoes recommended
  • safety glasses are required.
  • rough housing is not allowed.
  • hearing protection is required. Impact drivers are very loud.
  • Do not put yourself under a part of the dome that is propped up.
  • Take frequent breaks.
  • You may want to wear gloves.
  • Drink penty of water.
  • Wear sunscreen.
  • Have a big brimmed hat.
  • snug fitting long sleeve clothes recommended for sun protection
  • less flammable (cotton) clothes if using an angle grinder. or cut off