Length Table

A	Yellow	3.958	47.496
B	Blue	4.638	55.656
C	Red	4.429	53.148
D	Black	4.938	59.256
E	Green	4.562	54.744
F	Orange	4.821	57.852
G	Silver	5.013	60.156
H	Pink	5.243	62.916
I	Brown	5.274	63.288

Side 26.916 29.916 Height 23.30993977 26.30993977

Labor

A small crew is normally dedicated to this task. It normally takes about 2 days.

Safety

This may not be a complete list. 
  • Ask questions, see something say something.
  • We have deburred conduit, but there may still be sharp things.
  • Team lift, communication and coordination of the team is important.
  • safety glasses are required.
  • rough housing is not allowed.
  • hearing protection is required. Impact drivers are very loud.
  • Do not put yourself under a part of the dome that is propped up.
  • Take frequent breaks.
  • You may want to wear gloves.
  • Drink penty of water.
  • Wear sunscreen.
  • Have a big brimmed hat.