Prime Dome Construction
Jump to navigation
Jump to search
Length Table
A Yellow 3.958 47.496 B Blue 4.638 55.656 C Red 4.429 53.148 D Black 4.938 59.256 E Green 4.562 54.744 F Orange 4.821 57.852 G Silver 5.013 60.156 H Pink 5.243 62.916 I Brown 5.274 63.288
Side 26.916 29.916 Height 23.30993977 26.30993977
Tools
2 impact drivers, 4 chargers, 6 batteries(previously 2ah but bigger are mote available now) a ratchet, 3 correct size sockets with impact . 2 channel lock style pliers big enough to grab wing nuts.
member construction
Drill bit drill cuttoff wheel, measuring tape, press to squish the member ends flat, flap disk or grinder to deburr.
bolt specifications head size uses x socket
Tarp notes
Labor
A small crew is normally dedicated to this task. It normally takes about 2 days.
Safety
This may not be a complete list.
- Ask questions, see something say something.
- We have deburred conduit, but there may still be sharp things.
- Team lift, communication and coordination of the team is important.
- Closed toe shoes recommended
- safety glasses are required.
- rough housing is not allowed.
- hearing protection is required. Impact drivers are very loud.
- Do not put yourself under a part of the dome that is propped up.
- Take frequent breaks.
- You may want to wear gloves.
- Drink penty of water.
- Wear sunscreen.
- Have a big brimmed hat.
- snug fitting long sleeve clothes recommended for sun protection
- less flammable (cotton) clothes if using an angle grinder. or cut off