Difference between revisions of "Prime Dome Construction"
m (tools needed for building) |
(→Labor: procedures partial) |
||
Line 32: | Line 32: | ||
A small crew is normally dedicated to this task. | A small crew is normally dedicated to this task. | ||
It normally takes about 2 days. | It normally takes about 2 days. | ||
+ | ==Roles== | ||
+ | *Supervisor -- stands and watches | ||
+ | * Impactor | ||
+ | * Pattern layer this person preps the poles for the next stage and helps make sure the pattern is followed | ||
+ | * Nut holder -- this person holds the wing nut with a pair of pliars | ||
+ | * Lifter, 1 or 2, holds the | ||
+ | |||
+ | It is easier to connect pieces at waste height. so pattern layer will loosly get bolt on a step ahead of the snuggers while there is slack, and then the lifters can align and pull things together at waste height, then weight can also go on the new member right away allowing easier lifting. | ||
+ | |||
+ | We order the members so that when we disconnect things the lower ones can come off first. | ||
+ | so when we are putting things up the bolt stack is: | ||
+ | the ones going to a higher level are closer to the bolt head, and the horizontal ones are closer to the wing nut. then when the next layer gets added | ||
+ | |||
+ | Slack and play is sometimes nice, we go back around and zap the bolts with the impact. | ||
+ | |||
+ | We add tarps before the thing gets too high. | ||
=Safety= | =Safety= |
Revision as of 07:44, 22 June 2024
Length Table
A Yellow 3.958 47.496 B Blue 4.638 55.656 C Red 4.429 53.148 D Black 4.938 59.256 E Green 4.562 54.744 F Orange 4.821 57.852 G Silver 5.013 60.156 H Pink 5.243 62.916 I Brown 5.274 63.288
Side 26.916 29.916 Height 23.30993977 26.30993977
Tools
2 impact drivers, 4 chargers, 6 batteries(previously 2ah but bigger are mote available now) a ratchet, 3 correct size sockets with impact . 2 channel lock style pliers big enough to grab wing nuts.
member construction
Drill bit drill cuttoff wheel, measuring tape, press to squish the member ends flat, flap disk or grinder to deburr.
bolt specifications head size uses x socket
Tarp notes
Labor
A small crew is normally dedicated to this task. It normally takes about 2 days.
Roles
- Supervisor -- stands and watches
- Impactor
- Pattern layer this person preps the poles for the next stage and helps make sure the pattern is followed
- Nut holder -- this person holds the wing nut with a pair of pliars
- Lifter, 1 or 2, holds the
It is easier to connect pieces at waste height. so pattern layer will loosly get bolt on a step ahead of the snuggers while there is slack, and then the lifters can align and pull things together at waste height, then weight can also go on the new member right away allowing easier lifting.
We order the members so that when we disconnect things the lower ones can come off first. so when we are putting things up the bolt stack is: the ones going to a higher level are closer to the bolt head, and the horizontal ones are closer to the wing nut. then when the next layer gets added
Slack and play is sometimes nice, we go back around and zap the bolts with the impact.
We add tarps before the thing gets too high.
Safety
This may not be a complete list.
- Ask questions, see something say something.
- We have deburred conduit, but there may still be sharp things.
- Team lift, communication and coordination of the team is important.
- Closed toe shoes recommended
- safety glasses are required.
- rough housing is not allowed.
- hearing protection is required. Impact drivers are very loud.
- Do not put yourself under a part of the dome that is propped up.
- Take frequent breaks.
- You may want to wear gloves.
- Drink penty of water.
- Wear sunscreen.
- Have a big brimmed hat.
- snug fitting long sleeve clothes recommended for sun protection
- less flammable (cotton) clothes if using an angle grinder. or cut off